Hindalco Evaluates Tripling Gujarat Secondary Copper Capacity to 150,000 Tonnes
An expanded domestic processing facility in Pakhajan offers strong long-term off-take for scrap aggregators and e-waste collectors.
Hindalco is evaluating a major expansion of its secondary copper recycling plant at Pakhajan in Gujarat. The company is considering tripling its annual processing capacity from 50,000 tonnes to 150,000 tonnes.
Margins depend on steady off-take.
The Pakhajan plant is approaching its planned December commissioning for the initial footprint. If approved, the proposed expansion will add 100,000 tonnes of annual capacity, turning the site into a major domestic destination for copper scrap.
| Facility Stage | Annual Capacity | Status |
|---|---|---|
| Initial Setup | 50,000 tonnes | December commissioning |
| Proposed Expansion | 150,000 tonnes | Under evaluation |
Stronger Domestic Demand
For regional scrap aggregators and e-waste collectors moving high volumes through local mandis, a massive facility expansion in Gujarat creates a direct domestic buyer for secondary metal. Processing secondary copper inside India reduces reliance on complex export routes and lowers overall freight overhead for yards.
A 150,000-tonne processing capacity gives aggregators confidence to secure larger bulk collection contracts from industrial generators. Smelters running at this scale require consistent feed to maintain operation, which supports reliable procurement pricing.
Preparing Supply Pipelines
The initial phase remains on track for December commissioning. Supply networks, from regional aggregators down to local kabadiwali collections, will see fresh demand as secondary processing expands.
Aggregators handling copper wire, armatures, and e-waste should align supply routes ahead of the site coming online. Building direct delivery ties with large domestic plants helps yards maintain working capital flow and protect operational margins.